Posted by William Spates on May 1st, 2003 02:02 PM
In reply to Slab............... by doug seibert on April 27th, 2003 04:28 AM [Go to top of thread]

2 of 2 people found this post helpful

Moderator Post:
> Concrete Formula by Handyman on 05/19/2005

I had a post tension slab poured for my home, but 3/4 thru the pour the contractor ran out of concrete. It was about an 1 1/2 hours before the pour proceeded. Does this constitute a cold joint and should the slab be ripped out and redone?